Effia-Kwesimintsim Municipal Assembly Infrastructure Analytics

Overview.

Statistical snapshot of CoST-ST. Gh. EKMA projects only

Projects
14
Disclosed by this entity
Sectors
5
With active projects
Contractors
11
Delivering these projects
Project Budget
₵26.01M
GHS 26,010,936.32
Contract Price
₵26.70M
GHS 26,696,026.93
Completion Cost
₵32.52M
GHS 32,518,099.51
Top 5 Sectors

Sectors ranked by number of disclosed projects

  1. 01Transport & Roads 6 projects
  2. 02Housing & Buildings 3 projects
  3. 03Health 3 projects
  4. 04Education 1 project
  5. 05Water & Sanitation 1 project
Value for Money

Proportion of projects with final value greater than budget

  • Final value greater than budget 21.43%
  • Completed within budget 78.57%
Land & Settlement Impact

Proportion of projects with land and settlement impact assessment

  • With land and settlement impact 50.00%
  • Without land and settlement impact 50.00%
Procurement Methods

Value of contract awards by procurement method

MethodsTotal GHS 26,696,026.93
  • Open Competitive Tendering GHS 26,696,026.93
Top 5 Funding Sources

Funders ranked by value of project budget contributions