Project Identification
- Project Reference Number
- WR/AWMA/DACF/MP/WKS/NCT/25/2024
- Project Name
- Completion of CHIP Compound
- Sector
- Health
- Project Type
- New Construction
- Project Location
- Western Region
- Purpose
- Improves health service access, community wellbeing, and creates temporary employment
- Project Description
- Completion of CHIP compound with building, utilities, landscaping, and furniture to enhance community health services
Project Preparation
- Project Scope
- Completion of structural, finishing, electrical, plumbing works, furniture provision, site landscaping, and handover to ensure a fully functional CHIP compound
- Environmental Impact
- EPA Category: C – Minimal environmental impact : dust, noise, and waste managed on-site
- Land and Settlement Impact
- None – project within allocated compound with no displacement
- Design Standard
- Ghana Building Code, LGWD, and public health facility standards.
- Expected Life of Asset
- 25–30 years, assuming regular maintenance and proper use
- Risk Assessment
- Delays, cost overruns, H&S, environmental, compliance | Mitigation: Supervision, safety, inspections
- Funding
-
MP’s Common Fund
District Assemblies Common Fund (DACF)
GHS 176,522.43
- Project Budget
- GHS 176,522.43
- Project Budget Approval Date
- Mon Jun 03 2024
Project Completion
- Project Status
- Completed
- Completion Cost
- GHS 172,217.00
- Completion Date
- Mon Sep 30 2024
- Scope at Completion
- Buildings completed, utilities functional, furniture installed, and site handed over