Project Identification
- Project Reference Number
- WR/AWMA/WKS/DACF/03/2025
- Project Name
- Construction of 18 No. Mechanised boreholes
- Sector
- Water & Sanitation
- Project Type
- New Construction
- Project Location
- Western Region
- Purpose
- Improves access to safe water, public health, and household productivity
- Project Description
- Construction and mechanisation of 18 boreholes to improve access to safe drinking water across Ahanta West Municipality
Project Preparation
- Project Scope
- Borehole drilling, mechanisation, headworks, electrical connections, testing, and commissioning
- Environmental Impact
- Minimal impact; short-term disturbance during drilling managed appropriately.
- Land and Settlement Impact
- None—facilities sited on approved community land
- Design Standard
- CWSA and Water Resources Commission standards
- Expected Life of Asset
- Borehole: 30–40 years
Pumps: 10–15 years
- Risk Assessment
- Risks: Dry holes, equipment failure, power issues
Mitigation: Surveys, QA, maintenance planning
- Funding
-
District Assemblies Common Fund
District Assemblies Common Fund (DACF)
GHS 2,042,145.00
- Project Budget
- GHS 2,042,145.00
- Project Budget Approval Date
- Mon Dec 08 2025
Project Completion
- Project Status
- Completed
- Completion Date
- Tue Jul 07 2026
- Scope at Completion
- Boreholes completed, mechanised, tested, and handed over
Questions about this project?
This project is disclosed by
Ahanta West Municipal Assembly.
Citizens have the right to ask questions about public infrastructure.