Project Identification
- Project Reference Number
- WR/STMA/DACF/WKS/NCT/011/2025
- Project Name
- CONSTRUCTION OF FENCE WALL AND SECTIONAL REPAIR OF ROOF LEAKAGES FOR BISHOP O'RORKE ANGLICAN BASIC SCHOOL AT TAKORADI
- Sector
- Education
- Sub sector
- Basic Schools
- Project Type
- Other
- Project Location
- Western Region
- Purpose
- To enhance the safety and security of pupils, teachers, and school property through the construction of a fence wall, while undertaking sectional repairs of leaking roof areas to prevent water damage, improve classroom conditions, and provide a safe, conducive and comfortable teaching and learning environment.
- Project Description
- CONSTRUCTION OF FENCE WALL AND SECTIONAL REPAIR OF ROOF LEAKAGES.
4
Quality Education
Project Preparation
- Project Scope
- CONSTRUCTION OF FENCE WALL AND SECTIONAL REPAIR OF ROOF LEAKAGES.
- Environmental Impact
- Minor construction and dust noise; mitigated by dust screening and restricted working hours.
- Land and Settlement Impact
- No resettlement.
- Expected Life of Asset
- 50
- Funding
-
ESTEK VISION LIMITED.
Public Payment
- Project Budget
- GHS 445,585.00
- Project Budget Approval Date
- Wed Jul 30 2025
- Contact Details
-
info@stma.gov.gh
Tender Management
Initiation
- Procuring Entity
- Sekondi-Takoradi Metropolitan Assembly
- Procuring Entity Contact Details
-
info@stma.gov.gh
- Procurement Method
- Open Competitive Tendering
- Process Description
- CONSTRUCTION OF FENCE WALL AND SECTIONAL REPAIR OF ROOF LEAKAGES
Award
- Number of Firms Tendering
- 1
- Cost Estimate
- GHS 445,585.00
Contracting
- Contract Administrative Entity
- Sekondi-Takoradi Metropolitan Assembly
- Contract Type
- Works
- Contract Title
- CONSTRUCTION OF FENCE WALL AND SECTIONAL REPAIR OF ROOF LEAKAGES FOR BISHOP O'RORKE ANGLICAN BASIC SCHOOL AT TAKORADI
- Contract Identification
- WR/STMA/DACF/WKS/NCT/011/2025
- Contract Price
- GHS 441,240.00
- Contract Scope of Work
- CONSTRUCTION OF FENCE WALL AND SECTIONAL REPAIR OF ROOF LEAKAGES
- Contract Start Date
- Fri Oct 24 2025
- Contract Duration
-
From: Fri Oct 24 2025
To: ongoing
| # | Name of Firm | Role |
| 1 |
ESTEK VISION LIMITED. |
Lead Contractor |
- Contract Status
-
Completed
Project Completion
- Project Status
- Completed
- Completion Cost
- GHS 440,042.55
- Completion Date
- Wed Feb 25 2026
- Scope at Completion
- CONSTRUCTION OF FENCE WALL AND SECTIONAL REPAIR OF ROOF LEAKAGES AND EXTERNAL PAINTING OF FIRST FLOOR.