Home / Projects / Completion of Teachers Quarters and Repa...
Education Completed

Completion of Teachers Quarters and Repairs of 2-Unit 3-Bedroom Semi-Detached Bungalow at Shama

The project involves the completion of the existing teachers’ quarters and rehabilitation of a two-unit, three-bedroom semi-detached bungalow at Shama. The intervention seeks to improve the condition, safety and function...

Western Region GHA/WR/SDA/006 CoST Western Region Download OC4IDS JSON

Project Summary

Sector
Education
Location
Western Region
Stage
Identification
Contracting Entity
Shama District Assembly
Publication DateThu Nov 19 2026
Disclosed Values
BudgetGHS 647,910.00
ContractGHS 543,951.90
Project Identification
Project Reference Number
GHA/WR/SDA/006
Project Name
Completion of Teachers Quarters and Repairs of 2-Unit 3-Bedroom Semi-Detached Bungalow at Shama
Sector
Education
Sub sector
Basic Schools
Project Type
New Construction
Project Location
Western Region
Purpose
To provide decent and improved residential accommodation for teachers and educational personnel in Shama to enhance staff welfare, attract qualified teachers and improve the delivery of quality education.
Project Description
The project involves the completion of the existing teachers’ quarters and rehabilitation of a two-unit, three-bedroom semi-detached bungalow at Shama. The intervention seeks to improve the condition, safety and functionality of the residential facilities to provide a conducive living environment for teachers.
4 Quality Education
Project Preparation
Project Scope
Completion of outstanding works on the teachers’ quarters and rehabilitation of the two-unit, three-bedroom semi-detached bungalow, including roofing, ceiling, flooring, plumbing, electrical installations, kitchen, bathroom, painting and other finishing works.
Environmental Impact
"Environmental Impact: Minor dust, noise and construction debris may arise during rehabilitation, with minimal environmental disturbance through proper waste disposal. Social Impact: Improved teachers’ accommodation, staff welfare, motivation and retention, contributing to better educational service delivery."
Social Impact
"Environmental Impact: Minor dust, noise and construction debris may arise during rehabilitation, with minimal environmental disturbance through proper waste disposal. Social Impact: Improved teachers’ accommodation, staff welfare, motivation and retention, contributing to better educational service delivery."
Project Budget
GHS 647,910.00
Project Budget Approval Date
Tue Oct 28 2025
Tender Management

Initiation

Procuring Entity
Shama District Assembly
Procurement Method
Open Competitive Tendering
Process Description
N/A

Award

Number of Firms Tendering
4

Contracting

Contract Administrative Entity
Shama District Assembly
Contract Type
Works
Contract Title
Project: Completion of Teachers Quarters and Repairs of 2-Unit 3-Bedroom Semi-Detached Bungalow at Shama
Contract Identification
GHA/WR/SDA/006
Contract Price
GHS 543,951.90
Contract Scope of Work
N/A
Contract Status
Completed
Contract Implementation

Funds Disbursed

Disbursed: GHS 0.00 Contract value: GHS 543,951.90

Site Photos

Project Completion
Project Status
Completed

Questions about this project?

This project is disclosed by Shama District Assembly. Citizens have the right to ask questions about public infrastructure.

Location