Sekondi-Takoradi Metropolitan Assembly Infrastructure Analytics

Value for Money.

Time and cost overrun analysis STMA projects only

Budget vs Completion Cost
₵1.60M
Difference between approved project budget and completion cost GHS 1,597,420.20
Contract Price vs Completion Cost
₵2.34M
Difference between contract price and completion cost GHS 2,341,527.20
Time Overruns

Proportion of projects completed later than the planned contract end date

  • Time overrun 18.75%
  • Completed on time 81.25%
By Funding Source

Top 5 funding sources with time overrun

  • AGENCE FRANÇAISE DE DÉVELOPPEMENT 1 project
  • EUROPEAN UNION (EU) 1 project
Cost Overruns

Proportion of projects with completion cost above the contracted total

  • Cost overrun GHS 106,889.02
  • Within contract value 12 projects
By Funding Source

Value of cost overrun by funding source

  • DACF - RESPONSIVENESS FACTOR GRANT GHS 63,232.67
  • EUROPEAN UNION (EU) GHS 36,256.30
  • AGENCE FRANÇAISE DE DÉVELOPPEMENT GHS 0.05
Five Years to 2027

Contract price vs completion cost of completed projects, by completion year

Top 5 Contractors with Cost Overrun

Contracted total (navy) and the overrun portion (red)