Housing & Buildings Completed

Construction Out Patient Department Block

Out-Patient Department Block

Western Region CoST Western Region Download OC4IDS JSON

Project Summary

Sector
Housing & Buildings
Location
Western Region
Stage
Completion
Contracting Entity
Wassa East District Assembly
Publication DateThu Jul 09 2026
Disclosed Values
BudgetGHS 320,000.00
District Assemblies Common FundGHS 320,000.00
ContractGHS 329,965.65
Final CostGHS 329,965.00
Project Identification
Project Reference Number
Project Name
Construction Out Patient Department Block
Sector
Housing & Buildings
Project Type
New Construction
Project Location
Western Region
Purpose
To improve the standard of living through basic healthcare
Project Description
Out-Patient Department Block
3 Good Health and Well-Being
Project Preparation
Project Scope
Male & Female wards, consulting room, waiting area, pharmacy ,washrooms, records room, revenue and storage
Environmental Impact
No
Land and Settlement Impact
N/A
Design Standard
Yes
Expected Life of Asset
20 years
Risk Assessment
No
Funding
District Assemblies Common Fund District Assemblies Common Fund (DACF)
GHS 320,000.00 (original amount 55,334.83, currency unrecorded)
Project Budget
GHS 320,000.00
Project Budget Approval Date
Thu Oct 24 2019
Contact Details
info@weda.gov.gh
Tender Management

Initiation

Procuring Entity
Wassa East District Assembly
Procuring Entity Contact Details
info@weda.gov.gh
Procurement Process
National Competitive Tendering (Nct)
Procurement Method
Open Competitive Tendering

Award

Number of Firms Tendering
3
Cost Estimate
GHS 320,000.00

Contracting

Contract Type
Works
Contract Title
Construction 1No. Out-Patient Department Block at Atobiase
Contract Identification
WEDA/WKS/009/19
Contract Price
GHS 329,965.65
Contract Scope of Work
Male & Female Ward, Consulting Room, Waiting Area, Pharmacy Records Room/Revenue, Storage and Washrooms
Contract Start Date
Thu Nov 14 2019
Contract Duration
From: Thu Nov 14 2019
To: Tue Apr 14 2020
In Days: 152
Contract Status
Tendered
Project Completion
Project Status
Completed
Completion Cost
GHS 329,965.00
Completion Date
Fri May 14 2021
Scope at Completion
No changes