Completion of 1No Community Center

Completion of 1No. Community Center at Tetrem - Main hall with office and washroom

Western Region WR/TNMATWKS/DACF/01/26 CoST Western Region Download OC4IDS JSON

Project Summary

Sector
Social Protection & Community Development
Location
Western Region
Stage
Identification
Publication DateWed Nov 18 2026
Disclosed Values
BudgetGHS 300,000.00
DISTRICT ASSEMBLY COMMON FUND (DAC...GHS 300,000.00
ContractGHS 493,413.28
Project Identification
Project Reference Number
WR/TNMATWKS/DACF/01/26
Project Name
Completion of 1No Community Center
Sector
Social Protection & Community Development
Sub sector
Community Centres
Project Type
Other
Project Location
Western Region
Purpose
To provide a multipurpose social infrastructure for community gatherings, meetings, social events, and local government engagements in Tetrem.
Project Description
Completion of 1No. Community Center at Tetrem - Main hall with office and washroom
Project Preparation
Project Scope
Completion works comprising: main hall with office and washroom at front corners, plastering, floor/wall tiling, ceiling, painting, electrical & plumbing installations,
Environmental Impact
Minor dust, noise and construction waste during finishing. Mitigation: Water sprinkling for dust, day-time work, PPEs, proper waste disposal and septic tank for washroom. No resettlement.
Social Impact
Provides multipurpose hall with office and washroom for meetings, funerals, weddings, improves sanitation and social cohesion and creates local jobs.
Land and Settlement Impact
Land was provided by chiefs of the project community. No resettlement
Funding
DISTRICT ASSEMBLY COMMON FUND (DACF)
GHS 300,000.00
Project Budget
GHS 300,000.00
Project Budget Approval Date
Mon Mar 16 2026
Tender Management

Initiation

Procuring Entity
Tarkwa-Nsuaem Municipal Assembly
Procurement Process
Request for Quotations (RFQ
Procurement Method
National Competitive Tendering (NCT)
Process Description
Completion of 1No Community Center (main hall with office and washroom at front corners) including plastering, floor screeding and tiling, wall tiling for washroom, ceiling, painting, electrical wiring and plumbing, fixing of doors and windows, construction of septic tank and external works / site clearance.

Award

Number of Firms Tendering
3
Cost Estimate
GHS 493,413.28
Award Date
Tue Jun 16 2026

Contracting

Contract Administrative Entity
Tarkwa-Nsuaem Municipal Assembly
Contract Type
Works
Contract Title
Completion Of 1no Community Center
Contract Identification
WR/TNMATWKS/DACF/01/26
Contract Price
GHS 493,413.28
Contract Scope of Work
Completion of 1No Community Center (main hall with office and washroom at front corners) including plastering, floor screeding and tiling, wall tiling for washroom, ceiling, painting, electrical wiring and plumbing, fixing of doors and windows, construction of septic tank and external works / site clearance.
Contract Start Date
Tue Jun 16 2026
Contract Duration
From: Tue Jun 16 2026
To: ongoing
#Name of FirmRole
1 Ap Belstone Engineering Lead Contractor
Contract Status
Active

Questions about this project?

This project is disclosed by Tarkwa-Nsuaem Municipal Assembly. Citizens have the right to ask questions about public infrastructure.